W42191   Closed

09/16/2025, 02:00 pm   
Onsite
Normal
GDOE.5108: GDOE - PO 20233033-00 ActivPanel V9 75in Warranty
GDOE - PO 20233033-00 ActivPanel V9 75in Warranty [TOTAL ANNUAL HOURS: 4]
4
2
Alahas Pereda
No

Work Requested

Replace qty 2. defected mobile stand columns at PC Lujan Elementary School - Chamoru Immersion Classes 13 & 4.
Work Requested by: Evotia Perez

Items Dropped Off 0

Item Serial Number Notes

Work Completed 1

Summary of Tasks

Install mobile stand column and shelf in Chamoru Immersion Classes room 3 and 5 (Originally 13 and 4 but panels were moved).
Work Completed Technician Check-in Check-out Actual Hrs
1 Install mobile stand column and shelf in Chamoru Immersion Classes room 3 and 5 (Originally 13 and 4 but panels were moved). Kevin Hsueh
09/16/2025 01:30 pm 09/16/2025 03:00 pm 01:30

Parts and Materials 0

Item Serial Number Condition Qty Price Amount
TOTAL ($)   0.00

Comments For Internal Use only. 14

Date/Time Comment Tech
09/16/2025 08:46 am Created workorder. Alahas P.
09/16/2025 08:46 am Assigned: Kevin Hsueh Alahas P.
09/16/2025 08:46 am Updated status to Pending Schedule Alahas P.
09/16/2025 03:19 pm Check-in 09/16/2025 01:30 pm Kevin H.
09/16/2025 03:20 pm Arrived 09/16/2025 02:00 pm Kevin H.
09/16/2025 03:22 pm Updated status to Service Completed Kevin H.
09/16/2025 03:22 pm Work Order Tasks Added Kevin H.
09/16/2025 03:22 pm Check-out 09/16/2025 03:00 pm Kevin H.
09/16/2025 03:34 pm Service Completed Kevin H.
09/16/2025 03:34 pm Updated status to Pending Approval Kevin H.
09/16/2025 03:34 pm No Signature: Customer signed main Work Order. Kevin H.
09/17/2025 08:52 pm Approved. Chu H.
09/17/2025 08:52 pm Updated status to Submitted for Invoicing Chu H.
09/18/2025 10:00 am Updated status to Closed Jessica L.

Attachments 1

Filename
W42191