W42220   Closed

09/22/2025, 09:00 am   
Onsite
Normal
UOG0.4004: UOG PO251263 Verkada Installation 2025
UOG PO251263 Verkada Installation 2025 [TOTAL ANNUAL HOURS: 80]
67
7
Chu Hsieh
No

Work Requested

Installation of cabling and verkada cameras.
Work Requested by: Andrew Guihama

Items Dropped Off 0

Item Serial Number Notes

Work Completed 2

Summary of Tasks

Install tubing and 3 new network cables at Jubotron. Connect TPLink AP and new Verkada Bullet Camera. Confirmed both equipment powers up. Original bullet camera at Jubotron was not installed properly by previous vendor. Incorrect screws used and no weather proof gasket present. Advised Arty at UOG that original bullet camera may not be suggestable to use due to the previously vendor that installed incorrectly. Provided old camera to Arty, Arty to provide update to DSI on how UOG will proceed.
Work Completed Technician Check-in Check-out Actual Hrs
1 Run network cable for Atrium Verkada Fish Eye Camera from Atrium first floor to second floor switch room. Connect network and noted Verkada Fish Eye Camera powers on. Chu Hsieh
09/22/2025 09:00 am 09/22/2025 12:00 pm 03:00
2 Install tubing and 3 new network cables at Jubotron. Connect TPLink AP and new Verkada Bullet Camera. Confirmed both equipment powers up. Original bullet camera at Jubotron was not installed properly by previous vendor. Incorrect screws used and no weather proof gasket present. Advised Arty at UOG that original bullet camera may not be suggestable to use due to the previously vendor that installed incorrectly. Provided old camera to Arty, Arty to provide update to DSI on how UOG will proceed. Chu Hsieh
09/22/2025 01:00 pm 09/22/2025 04:30 pm 03:30

Parts and Materials 0

Item Serial Number Condition Qty Price Amount
TOTAL ($)   0.00

Comments For Internal Use only. 17

Date/Time Comment Tech
09/24/2025 11:48 am Created workorder. Chu H.
09/24/2025 11:48 am Assigned: Chu Hsieh Chu H.
09/24/2025 11:48 am Updated status to Scheduled Chu H.
09/24/2025 11:51 am Check-in 09/22/2025 09:00 am Chu H.
09/24/2025 11:54 am Arrived 09/22/2025 09:00 am Chu H.
09/24/2025 11:55 am Updated status to In Progress Chu H.
09/24/2025 11:55 am Check-out 09/22/2025 12:00 pm Chu H.
09/24/2025 11:59 am Check-in 09/22/2025 01:00 pm Chu H.
09/24/2025 12:02 pm Updated status to Service Completed Chu H.
09/24/2025 12:02 pm Work Order Tasks Added Chu H.
09/24/2025 12:02 pm Check-out 09/22/2025 04:30 pm Chu H.
09/24/2025 02:36 pm Service Completed Chu H.
09/24/2025 02:36 pm Updated status to Pending Approval Chu H.
09/24/2025 02:36 pm No Signature: project Chu H.
09/24/2025 02:38 pm Approved. Chu H.
09/24/2025 02:38 pm Updated status to Submitted for Invoicing Chu H.
09/24/2025 02:59 pm Updated status to Closed Jessica L.

Attachments 1

Filename
W42220