UOG0.4004: UOG PO251263 Verkada Installation 2025
UOG PO251263 Verkada Installation 2025 [TOTAL ANNUAL HOURS: 80]
67
3
Alahas Pereda
No

Work Requested

we can proceed with scheduling the installation of the camera as-is on Wednesday, January 28 at 2:00 PM, so we can move toward closing out this PO. Prior to the installation, we kindly ask that Verkada Command be fully configured for the items below. Please let us know once the setup is complete, or if there’s anything you need from our end: • Maglock and push-to-exit button – Room 245 • Environmental sensor and horn speaker – Café Sirena
Work Requested by: Andrew Guihama

Items Dropped Off 0

Item Serial Number Notes

Work Completed 1

Summary of Tasks

- Mounted one old bullet camera to be facing opposite from the verkada camera. - Mounted maglock plate to the SBA room, found that exit button is not engaging the lock, checked wiring on the AC12 and PSU and no signs of damages found. Possible wiring arrangement error. Will conduct troubleshooting another day when an updated diagram is created.
Work Completed Technician Check-in Check-out Actual Hrs
1 - Mounted one old bullet camera to be facing opposite from the verkada camera. - Mounted maglock plate to the SBA room, found that exit button is not engaging the lock, checked wiring on the AC12 and PSU and no signs of damages found. Possible wiring arrangement error. Will conduct troubleshooting another day when an updated diagram is created. Sean Bacani
01/28/2026 01:50 pm 01/28/2026 04:10 pm 02:20

Parts and Materials 0

Item Serial Number Condition Qty Price Amount
TOTAL ($)   0.00

Comments For Internal Use only. 14

Date/Time Comment Tech
01/28/2026 01:50 pm Created workorder. Alahas P.
01/28/2026 01:50 pm Assigned: Sean Bacani Alahas P.
01/28/2026 01:50 pm Updated status to Scheduled Alahas P.
01/28/2026 05:09 pm Check-in 01/28/2026 01:50 pm Sean B.
01/28/2026 05:10 pm Arrived 01/28/2026 02:00 pm Sean B.
01/28/2026 05:12 pm Updated status to Service Completed Sean B.
01/28/2026 05:12 pm Work Order Tasks Added Sean B.
01/28/2026 05:12 pm Check-out 01/28/2026 04:10 pm Sean B.
01/28/2026 05:15 pm Service Completed Sean B.
01/28/2026 05:15 pm Updated status to Pending Approval Sean B.
01/28/2026 05:15 pm No Signature: - UOG Verkada Project Sean B.
01/29/2026 07:22 pm Approved. Chu H.
01/29/2026 07:22 pm Updated status to Submitted for Invoicing Chu H.
01/30/2026 04:18 pm Updated status to Closed Jessica L.