Arrive onsite at Ross #1902 and worked with Danny from Ross Help Desk. Proceed to remove old APC 750 UPS and install new APC 750 UPS. Confirmed with Danny that he can see the server is up and APC 750 UPS can be consoled in to. Cleared to leave site by Danny. Pack up the old APC 750 UPS and brought to local FedEx to ship back to Level 10 using provided return label.
|
Work Completed |
Technician |
Check-in |
Check-out |
Actual Hrs |
| 1 |
Arrive onsite at Ross #1902 and worked with Danny from Ross Help Desk. Proceed to remove old APC 750 UPS and install new APC 750 UPS. Confirmed with Danny that he can see the server is up and APC 750 UPS can be consoled in to. Cleared to leave site by Danny. Pack up the old APC 750 UPS and brought to local FedEx to ship back to Level 10 using provided return label. |
Kevin Hsueh
|
11/22/2024 06:00 am |
11/22/2024 08:00 am |
02:00
|