| Item | Serial Number | Notes |
|---|
| Work Completed | Technician | Check-in | Check-out | Actual Hrs | |
|---|---|---|---|---|---|
| 1 | Setup 3 laptops to print locally and share 3 printers. Was able to print to VersaLink printers but unable to add AltaLink C8145 as wrong USB cable was ordered. Will return Wednesday morning to continue configuration |
Chu Hsieh |
01/21/2025 01:30 pm | 01/21/2025 05:59 pm | 04:29 |
| 2 | Check-in |
Chu Hsieh |
01/21/2025 01:30 pm | ||
| 3 | Finish setting up Altalink C8145 to use USB connection for printing on all 3 laptops. Unable to access share printers on Anne laptop due to company group policy. |
Chu Hsieh |
01/22/2025 09:30 am | 01/22/2025 12:20 pm | 02:50 |
| Item | Serial Number | Condition | Qty | Price | Amount | |
|---|---|---|---|---|---|---|
| TOTAL ($) | 0.00 | |||||
| Date/Time | Comment | Tech |
|---|---|---|
| 01/21/2025 11:53 am | Created workorder. | Chu H. |
| 01/21/2025 11:53 am | Assigned: Chu Hsieh | Chu H. |
| 01/21/2025 11:53 am | Updated status to Pending Schedule | Chu H. |
| 01/21/2025 05:58 pm | Check-in 01/21/2025 01:30 pm | Chu H. |
| 01/21/2025 05:59 pm | Check-in 01/21/2025 01:30 pm | Chu H. |
| 01/21/2025 06:00 pm | Updated status to In Progress | Chu H. |
| 01/21/2025 06:00 pm | Check-out 01/21/2025 05:59 pm | Chu H. |
| 01/22/2025 12:19 pm | Check-in 01/22/2025 09:30 am | Chu H. |
| 01/22/2025 12:25 pm | Updated status to Service Completed | Chu H. |
| 01/22/2025 12:25 pm | Work Order Tasks Added | Chu H. |
| 01/22/2025 12:25 pm | Check-out 01/22/2025 12:20 pm | Chu H. |
| 01/22/2025 12:27 pm | Customer Signature Posted | Chu H. |
| 01/22/2025 12:28 pm | Service Completed | Chu H. |
| 01/22/2025 12:28 pm | Updated status to Pending Approval | Chu H. |
| 01/22/2025 12:30 pm | Approved. | Chu H. |
| 01/22/2025 12:30 pm | Updated status to Submitted for Invoicing | Chu H. |
| 01/22/2025 01:29 pm | Updated status to Invoiced | Jessica L. |
| Filename | |
|---|---|
| W41674 | |