| Item | Serial Number | Notes |
|---|
| Work Completed | Technician | Check-in | Check-out | Actual Hrs | |
|---|---|---|---|---|---|
| 1 | Joanna called saying no ones able to access server and network. There was a power outage at Hagatna last night causing server to improperly shutdown. Will suggest to KHLG to replace the Back-UPS pro UPS to Smart-UPS to allow server to properly shutdown and restart on power failures. Work with Joanna to restart server and Dropbox PC. Check for any issues. |
Chu Hsieh |
08/23/2019 08:30 am | 08/23/2019 09:06 am | 00:36 |
| Item | Serial Number | Condition | Qty | Price | Amount | |
|---|---|---|---|---|---|---|
| TOTAL ($) | 0.00 | |||||
| Date/Time | Comment | Tech |
|---|---|---|
| 08/23/2019 03:00 pm | Updated status to Invoiced | Jessica L. |
| 08/23/2019 09:11 am | Updated status to Submitted for Invoicing | Chu H. |
| 08/23/2019 09:11 am | Approved. | Chu H. |
| 08/23/2019 09:11 am | No Signature: Remote support with Joanna | Chu H. |
| 08/23/2019 09:11 am | Updated status to Pending Approval | Chu H. |
| 08/23/2019 09:11 am | Service Completed | Chu H. |
| 08/22/2019 11:10 pm | Updated billable hours to: 01.00 | Chu H. |
| 08/23/2019 09:10 am | Modified workorder. | Chu H. |
| 08/23/2019 09:10 am | Updated status to Service Completed | Chu H. |
| 08/23/2019 09:10 am | Check-out 08/23/2019 09:06 am | Chu H. |
| 08/23/2019 09:10 am | Updated status to Scheduled | Chu H. |
| 08/23/2019 09:06 am | Check-in 08/23/2019 08:30 am | Chu H. |
| 08/23/2019 09:05 am | Updated status to Scheduled | Chu H. |
| 08/23/2019 09:05 am | Assigned: Chu Hsieh | Chu H. |
| 08/23/2019 09:05 am | Created workorder. | Chu H. |
| Filename | |
|---|---|
| W36791 | |