W35011   Invoiced

03/16/2018, 03:30 pm   
Onsite
Normal
AFLC.4008: Aflac Regional Office - Network Project
Network Project [TOTAL HOURS: 25]
-12
2
Jordan Gimmen
No
026877

Work Requested

Install new switches and APs Relocate server/network equipment
Work Requested by:

Items Dropped Off 0

Item Serial Number Notes

Work Completed 1

Work Completed Technician Check-in Check-out Actual Hrs
1 Replaced/installed switches. Relocated server and network equipment. Confirmed all server/network equipment is operational. Set up and configured AP. Signal strength is good throughout the office space. Jordan Gimmen
03/16/2018 03:30 pm 03/16/2018 04:30 pm 01:00

Parts and Materials 0

Item Serial Number Condition Qty Price Amount
TOTAL ($)   0.00

Comments For Internal Use only. 11

Date/Time Comment Tech
03/23/2018 10:52 am Updated status to Invoiced/Closed Jessica L.
03/16/2018 06:21 pm Updated status to Submitted for Invoicing Chu H.
03/16/2018 04:17 pm Updated status to Pending Approval Jordan G.
03/16/2018 04:30 pm Arrived. Jordan G.
03/16/2018 05:17 pm Updated billable hours to: 1 Jordan G.
03/16/2018 04:16 pm Updated status to Service Completed Jordan G.
03/16/2018 03:30 pm Arrived. Jordan G.
03/16/2018 03:30 pm Check-in. Jordan G.
03/16/2018 04:14 pm Updated status to Scheduled Jordan G.
03/16/2018 04:14 pm Assigned: Jordan Gimmen Jordan G.
03/16/2018 04:14 pm Created workorder. Jordan G.

Attachments 1

Filename
W35011