W37487   Invoiced

KHLG Associates
Odilia Bautista (671-478-5454)
06/10/2020, 09:00 am   
Onsite
Service Contract
KHLG.6001: KHLG - Service Contract (10/01/19 - 09/30/20)
KHLG - Service Contract (10/01/19 - 09/30/20) : $0.00 / hour
0
Kylene Hsieh
Yes
Joanna
06/10/2020
029078

Work Requested

AARF Office - Replace Mikee's monitor with 28" new monitor - Replace following T46S with T58 phones x 284 Mikee (IP: 10.90.90.33) - Troubleshoot and possibly re terminate the previously installed line to Mikee’s. Network switch showing it is not running at Gigabit. - Bring all the T46S back to DSI office
Work Requested by: Odilia Bautista

Items Dropped Off 0

Item Serial Number Notes

Work Completed 1

Summary of Tasks

Deliver and install monitor for Mikee, test ethernet line for Mikee, test passed.
Work Completed Technician Check-in Check-out Actual Hrs
1 Deliver and install monitor for Mikee, test ethernet line for Mikee, test passed. Elser Edward
06/10/2020 08:59 am 06/10/2020 09:58 am 00:59

Parts and Materials 0

Item Serial Number Condition Qty Price Amount
TOTAL ($)   0.00

Comments For Internal Use only. 30

Date/Time Comment Tech
06/23/2020 02:44 pm Updated status to Invoiced Jessica L.
06/10/2020 05:18 pm Updated status to Submitted for Invoicing Chu H.
06/10/2020 05:18 pm Approved. Chu H.
06/10/2020 10:05 am Updated status to Pending Approval Elser E.
06/10/2020 10:05 am Service Completed Elser E.
06/10/2020 10:01 am Customer Signature Posted Elser E.
06/10/2020 09:59 am Check-out 06/10/2020 09:58 am Elser E.
06/10/2020 09:59 am Work Order Tasks Added Elser E.
06/10/2020 09:59 am Updated status to Service Completed Elser E.
06/10/2020 09:23 am Arrived 06/10/2020 09:22 am Elser E.
06/10/2020 09:00 am Check-in 06/10/2020 08:59 am Elser E.
06/08/2020 05:15 pm Work requested modified- AARF Office - Replace Mikee's monitor with 28" new monitor - Replace following T46S with T58 phones x 284 Mikee (IP: 10.90.90.33) - Troubleshoot and possibly re terminate the previously installed line to Mikee’s. Network switch showing it is not running at Gigabit. - Bring all the T46S back to DSI office Kylene H.
06/08/2020 05:14 pm Work requested modified- AARF Office - Replace Mikee's monitor with 28" new monitor - Replace following T46S with T58 phones x 284 Mikee (IP: 10.90.90.33) - Troubleshoot and possibly re terminate the previously installed line to Mikee’s. Network switch showing it is not running at Gigabit. Kylene H.
06/08/2020 05:11 pm Work requested modified- AARF Office - Replace following T46S with T58 phones x 284 Mikee (IP: 10.90.90.33) - Troubleshoot and possibly re terminate the previously installed line to Mikee’s. Network switch showing it is not running at Gigabit. Kylene H.
06/08/2020 04:47 pm Modified workorder. Kylene H.
06/08/2020 04:47 pm Updated scheduled date/time from 06/09/2020 09:00 am to: 06/10/2020 09:00 am Kylene H.
06/08/2020 04:47 pm Updated Estimated Service Time (hrs) to Kylene H.
06/08/2020 04:40 pm Modified workorder. Kylene H.
06/08/2020 04:40 pm Updated status to Scheduled Kylene H.
06/08/2020 04:40 pm Unassigned: Chu Hsieh Kylene H.
06/08/2020 04:40 pm Assigned: Elser Edward Kylene H.
06/08/2020 04:40 pm Updated Estimated Service Time (hrs) to Kylene H.
06/08/2020 04:26 pm Work requested modified- AARF Office - remove Mikey's monitor and replace with 28" - phone replacement - troubleshoot the network cable - see Chu for more instructions Kylene H.
06/08/2020 03:43 pm Modified workorder. Kylene H.
06/08/2020 03:43 pm Unassigned: DSI Tech Kylene H.
06/08/2020 03:43 pm Assigned: Chu Hsieh Kylene H.
06/08/2020 03:43 pm Updated Estimated Service Time (hrs) to Kylene H.
06/08/2020 03:37 pm Updated status to Pending Schedule Kylene H.
06/08/2020 03:37 pm Assigned: DSI Tech Kylene H.
06/08/2020 03:37 pm Created workorder. Kylene H.

Attachments 1

Filename
W37487