W37849   Closed

09/28/2020, 09:00 am   
Onsite
Service Contract
GBHW.5008: GBHWC IWB Relocation PO P206A04122
GBHWC IWB Relocation PO P206A04122 [TOTAL ANNUAL HOURS: 6]
6
3
Kylene Hsieh
Yes
Charlene
09/28/2020

Work Requested

relocation of promethean board
Work Requested by: Charlene B. Cruz

Items Dropped Off 0

Item Serial Number Notes

Work Completed 2

Summary of Tasks

Relocate promethean board from 3rd floor to second floor.
Work Completed Technician Check-in Check-out Actual Hrs
1 Elser Edward
09/28/2020 08:59 am 09/28/2020 12:24 pm 03:25
2 Relocate promethean board from 3rd floor to second floor. Elser Edward
09/28/2020 01:51 pm 09/28/2020 03:10 pm 01:19

Parts and Materials 0

Item Serial Number Condition Qty Price Amount
TOTAL ($)   0.00

Comments For Internal Use only. 17

Date/Time Comment Tech
09/24/2020 12:35 pm Created workorder. Kylene H.
09/24/2020 12:35 pm Assigned: Elser Edward Kylene H.
09/24/2020 12:35 pm Updated status to Scheduled Kylene H.
09/28/2020 08:59 am Check-in 09/28/2020 08:59 am Elser E.
09/28/2020 09:15 am Arrived 09/28/2020 09:15 am Elser E.
09/28/2020 12:24 pm Updated status to In Progress Elser E.
09/28/2020 12:24 pm Check-out 09/28/2020 12:24 pm Elser E.
09/28/2020 01:51 pm Check-in 09/28/2020 01:51 pm Elser E.
09/28/2020 03:10 pm Customer Signature Posted Elser E.
09/28/2020 03:11 pm Updated status to Service Completed Elser E.
09/28/2020 03:11 pm Work Order Tasks Added Elser E.
09/28/2020 03:11 pm Check-out 09/28/2020 03:10 pm Elser E.
09/28/2020 03:11 pm Service Completed Elser E.
09/28/2020 03:11 pm Updated status to Pending Approval Elser E.
09/29/2020 02:23 pm Approved. Chu H.
09/29/2020 02:23 pm Updated status to Submitted for Invoicing Chu H.
09/29/2020 02:52 pm Updated status to Closed Jessica L.

Attachments 1

Filename
W37849