W38536   Closed

06/14/2021, 09:00 am   
Onsite
Normal
BLKC.3001: Black Construction - 3CX Project 2021
Black Construction - 3CX Project 2021 [TOTAL ANNUAL HOURS: 30]
30
3
Meryll Cruz
No

Work Requested

Elevator project
Work Requested by: GIAA

Items Dropped Off 0

Item Serial Number Notes

Work Completed 1

Summary of Tasks

Terminate 20 lines to patch panel
Work Completed Technician Check-in Check-out Actual Hrs
1 Terminate 20 lines to patch panel Meryll Cruz
06/14/2021 09:00 am 06/14/2021 12:00 pm 03:00

Parts and Materials 0

Item Serial Number Condition Qty Price Amount
TOTAL ($)   0.00

Comments For Internal Use only. 14

Date/Time Comment Tech
06/14/2021 11:43 am Created workorder. Meryll C.
06/14/2021 11:43 am Assigned: Meryll Cruz Meryll C.
06/14/2021 11:43 am Updated status to Scheduled Meryll C.
06/14/2021 12:26 pm Check-in 06/14/2021 09:00 am Kevin H.
06/14/2021 01:31 pm Arrived 06/14/2021 09:00 am Meryll C.
06/14/2021 01:32 pm Updated status to Service Completed Meryll C.
06/14/2021 01:32 pm Work Order Tasks Added Meryll C.
06/14/2021 01:32 pm Check-out 06/14/2021 12:00 pm Meryll C.
06/14/2021 01:33 pm Service Completed Meryll C.
06/14/2021 01:33 pm Updated status to Pending Approval Meryll C.
06/14/2021 01:33 pm No Signature: Poject Meryll C.
06/14/2021 05:52 pm Approved. Chu H.
06/14/2021 05:52 pm Updated status to Submitted for Invoicing Chu H.
06/15/2021 11:34 am Updated status to Closed Jessica L.

Attachments 1

Filename
W38536