Ran a trial installation of a flat panel on a problematic corner. Corner was not properly vertical, and trial run could not succeed - IT&E will need to adjust wall. Installed brackets onto curved panel.
|
|
Work Completed |
Technician |
Check-in |
Check-out |
Actual Hrs |
|
|
1 |
Ran a trial installation of a flat panel on a problematic corner. Corner was not properly vertical, and trial run could not succeed - IT&E will need to adjust wall. Installed brackets onto curved panel. |
Alyx Bradley
|
04/05/2022 09:32 am |
04/05/2022 03:59 pm |
06:27
|