Rerouted/reorganized cables and moved 2 network switches from server rack into wood cabinet. Perform tests with Colin and confirmed network is back up after relocation of switches and reroute of cables.
|
|
Work Completed |
Technician |
Check-in |
Check-out |
Actual Hrs |
|
|
1 |
Rerouted/reorganized cables and moved 2 network switches from server rack into wood cabinet. Perform tests with Colin and confirmed network is back up after relocation of switches and reroute of cables. |
Charles Rafanan
|
05/17/2022 02:30 pm |
05/17/2022 04:30 pm |
02:00
|