- Mounted Maglock PSU unit, and placed the backup battery inside.
- Mounted a Patch Panel and Switch to the existing server rack. Placed a UPS system at the bottom of the rack. Marked the first 6 ports to be used with ACS panels.
- Unable to open the rear door of the existing server rack, inquired Arthur and advised he will follow up.
- Mounted the new Switch and Patch Panel rack at the rear exit corner wall.
- Placed the Switch inside the rack along the UPS system, will be mounted next time.
|
|
Work Completed |
Technician |
Check-in |
Check-out |
Actual Hrs |
|
|
1 |
- Mounted Maglock PSU unit, and placed the backup battery inside.
- Mounted a Patch Panel and Switch to the existing server rack. Placed a UPS system at the bottom of the rack. Marked the first 6 ports to be used with ACS panels.
- Unable to open the rear door of the existing server rack, inquired Arthur and advised he will follow up.
- Mounted the new Switch and Patch Panel rack at the rear exit corner wall.
- Placed the Switch inside the rack along the UPS system, will be mounted next time. |
Sean Bacani
|
02/05/2026 01:20 pm |
02/05/2026 04:05 pm |
02:45
|