- Ran 6 CAT6e cables from the ACS panels to the Server Rack, non-terminated yet.
- Removed wiring holes from the AC62 and AC42.
- Walked through the building to analyze wiring and camera placements using the Camera Diagram. Assigned devices connected to the two switched based off the location of the devices in the diagram. The digital diagrams will be updated accordingly.
- Created labels for the 6 CAT6e cables.
|
|
Work Completed |
Technician |
Check-in |
Check-out |
Actual Hrs |
|
|
1 |
- Ran 6 CAT6e cables from the ACS panels to the Server Rack, non-terminated yet.
- Removed wiring holes from the AC62 and AC42.
- Walked through the building to analyze wiring and camera placements using the Camera Diagram. Assigned devices connected to the two switched based off the location of the devices in the diagram. The digital diagrams will be updated accordingly.
- Created labels for the 6 CAT6e cables. |
Sean Bacani
|
02/06/2026 01:30 pm |
02/06/2026 03:50 pm |
02:20
|